B.C. moves to hand Massey bridge design to the tunnel's own engineering firm without a competition

The B.C. government plans to give a contract to design a bridge to replace the George Massey Tunnel to COWI North America, the engineering firm the province hired in 2022 to oversee the new tunnel it had planned to build, without a competition.
The plan appears in a notice of intent posted on BC Bid at 3:31 p.m. Wednesday, a few hours after Premier Lorne Doerkson named the bridge design as the first of three "immediate" priorities following his cabinet's first meeting. The notice, issued by the Transportation Investment Corporation for the Transportation Ministry, says the province "is contemplating making a direct award of a contract to COWI North America Ltd." for "Design Services - George Massey Crossing."
A direct award, open to challenge until Dec. 9
A notice of intent is how B.C. public bodies announce that they plan to award a contract to one company without seeking bids. Other suppliers who believe they could do the work can file a challenge; the notice includes a challenge form and closes at 2 p.m. on Dec. 9. The value and scope of the contract are in a document attached to the notice, which BC Bid places behind a CAPTCHA check; ThinkPol has not reviewed it.
COWI is not new to the crossing. In February 2022, the province awarded it a $15-million contract as "owner's engineer" for the eight-lane immersed tube tunnel, one of nine contracts worth $56.7 million announced at the time. COWI's own 2019 technical memo on immersed tunnel options for the crossing is among the project's published planning documents, and the company designed the original tunnel, which opened in 1959.
Doerkson said Wednesday the notice would ask the current contractor to do the work, and that cabinet would review the numbers before a final decision, which he hoped would come before Christmas. "I am, obviously, very big on 'bridge' right now, but I do want to understand a few things just before that final decision happens," he told reporters.
The mandate letter Doerkson released Tuesday tells Transportation Minister Trevor Halford to "provide Cabinet with all the information needed to make a final decision on the George Massey Tunnel Replacement."
Where the tunnel stands
The NDP government announced the eight-lane tunnel in 2021 at an estimated $4.15 billion, with completion in 2030. In July 2026, it put the cost at $8.5 billion. In June, it ended its agreement with the Cross Fraser Partnership, the consortium chosen to design and build the tunnel, after the two sides could not agree on a price for the main construction phase. It then split the remaining work into five smaller contracts, none of which has been awarded. Early works and site preparation have been under way on Deas Island since January.
TI Corp's 2026/27 service plan, published in February, says the tunnel's cost and schedule "are being updated" and that the province would not release a new estimate before a contract is signed because of "commercial sensitivities."
The tunnel's environmental assessment, which was weeks from being referred to ministers, was paused at TI Corp's request on Nov. 17 during the transition. Ottawa has committed up to $3 billion toward the crossing, and federal Transport Minister Steven MacKinnon said on Oct. 30 that Ottawa would support "whatever way the Premier tells us to" cross the river. The government has not released a cost estimate or business case for a bridge.
The other two priorities
Doerkson's second priority was removing SOGI 123, a set of resources on sexual orientation and gender identity for schools, from government websites "effective immediately." A provincial release said the Education Ministry will work with school districts to remove the material from schools.
The third was a return to the office for the B.C. Public Service. In a Nov. 24 letter to Kim Henderson, head of the public service, Doerkson asked her to "begin preparation for a phased return to the workplace, including a review of existing remote work arrangements, office capacity, and any accommodations that may be required," and to report back on timelines and "any policy, legal, or collective agreement issues." The letter does not set a number of days; Doerkson said Wednesday that those who can work from an office will be back "five days a week."
The B.C. General Employees' Union said it had not been consulted and that it had written to the premier asking him to pause any changes to in-office requirements until the union meets with the government. It told members with remote or telework agreements to "continue as usual until your supervisor tells you otherwise."
Sources: BC Bid, Notice of Intent NOI27-GMC-017, "Design Services - George Massey Crossing," issued Nov. 25, 2026; B.C. Ministry of Transportation and Infrastructure, news release on Highway 99 Tunnel Program contracts, Feb. 9, 2022; COWI North America, "George Massey Crossing Immersed Tube Tunnel Technical Summary," Nov. 2019; Transportation Investment Corporation, 2026/27–2028/29 Service Plan; mandate letter from Premier Lorne Doerkson to Trevor Halford, Nov. 24, 2026; Premier Doerkson's news conference, Nov. 25, 2026, as reported by CBC News; Doerkson letter to Kim Henderson, Nov. 24, 2026, as published by CHEK News; BCGEU statement, Nov. 25, 2026; ENR and Daily Hive reporting on the tunnel contract and federal funding.