Telus quits Vancouver AI data centres as B.C. holds off on deciding who gets the power

By ThinkPol · · 3 min read

Server racks with green status lights in a data centre
Dreamstime

Telus has pulled out of the two Vancouver AI data centres it announced with developer Westbank six months ago. The power those projects would need is still undecided: BC Hydro has yet to say which AI and data-centre projects will get electricity, and has held back its decision until the new provincial government takes office.

"Telus has decided not to proceed with co-developing two previously announced Vancouver data centres with Westbank," a company spokesperson told CBC News this week. Telus said it would focus instead on expanding its existing data centre in Kamloops, and gave no reason for the change. Westbank said it is "proceeding with the projects as planned, with a new partnership that will be announced in the coming months."

What Telus promised in May

In a May 11 news release, Telus described a three-site "Sovereign AI Factory" cluster in B.C.: the Kamloops expansion, a converted office building in Mount Pleasant known as M3, and a new 400,000-square-foot facility at 150 West Georgia Street beside B.C. Place. The company said the cluster would hold more than 60,000 Nvidia GPUs and reach over 150 megawatts by 2032, and that it was "leveraging an initial 85 megawatts (MW) of clean, renewable power secured from BC Hydro."

The Vancouver sites carried most of the project's public-benefit claims. Telus said waste heat from their liquid-cooling systems would feed the City of Vancouver's Neighbourhood Energy Utility in Mount Pleasant and Creative Energy's downtown district energy system, heating the equivalent of 150,000 homes, and that water use would be 90 per cent below a conventional data centre. Then-CEO Darren Entwistle said the cluster would inject $9 billion into the Canadian economy. Neither company has said whether those commitments will carry over to Westbank's new partner.

The project was also part of Ottawa's sovereign-AI push. Telus announced it alongside Evan Solomon, the federal Minister of Artificial Intelligence and Digital Innovation, under the federal Enabling Large-Scale Sovereign AI Data Centres initiative, with Telus, Westbank and the federal government "working together on the details."

Who gets the power is still undecided

Under Bill 31, the Energy Statutes Amendment Act, new AI and data-centre projects in B.C. must now compete for electricity. The province launched that process in January with an allocation target of up to 400 megawatts over the first two years, and said successful applicants would be notified in September 2026.

That has not happened. BC Hydro's Call for Demand page now says it received 15 applications "representing close to 800 megawatts (MW) in total load request," about twice the allocation target. It says that because a provincial election was called, "notifications are expected following the completion of the government transition period later this year." The decision on which projects get power will therefore fall to the incoming B.C. Conservative government.

Projects that were already far along in BC Hydro's interconnection queue, with a signed facilities study agreement for transmission or a design deposit for distribution, were exempted and continue under the old process. Telus has not said whether its 85 megawatts came through that route, or whether that power is tied to the Vancouver sites it is leaving. In a public question-and-answer document, an applicant asked BC Hydro whether the Bell and Telus projects, "that total well over 400 MW of capacity," would be treated separately. BC Hydro's answer: it "does not comment on particular projects and their load requests."

What happens next in Vancouver

The M3 conversion at 111 East 5th Avenue still needs a rezoning from industrial to comprehensive development to allow "Bulk Data Storage" in the existing building. The previous council pulled the application from its July 23 public hearing and told staff to consult further after the October election. The city's Shape Your City page now lists a new question-and-answer period from Dec. 2 to Dec. 15.

Council is also due to debate a motion this week from OneCity Coun. Lucy Maloney asking staff to recommend a regulatory framework for assessing AI data-centre rezonings. A similar motion from Maloney failed under the previous council in July. "AI data centres can have outsized impacts compared to other industrial and commercial uses," she told CBC.

Telus itself is in play. Quebecor has made a takeover offer reported at $31 billion. In a statement on Monday, Industry Minister Mélanie Joly said the government had "taken note of Quebecor's proposal," that the deal would be reviewed by the Competition Bureau and the CRTC, and that Ottawa "will not predetermine the outcomes."

Sources: TELUS news release, May 11, 2026; BC Hydro, 2026 Call for Demand for Emerging Industries and applicant Q&A; B.C. Ministry of Energy and Climate Solutions news release, Jan. 30, 2026; City of Vancouver, Shape Your City, 111 E 5th Avenue rezoning; Innovation, Science and Economic Development Canada, Nov. 16, 2026; CBC News.